Subscribe to UMHN

Subscribe
to UMHN and receive
important neighborhood information

CLICK HERE


UofR Clinical and Translational
Science Building (CTSB)

The University of Rochester Medical Center is pleased to announce that ground has been broken for the new Clinical and Translational Science Building (CTSB). Because of the location of this construction site, adjacent to the School of Nursing's Helen Wood Hall and within our neighborhood, the University wishes to keep neighbors informed about the progress of the building's construction.
Translational Science Building

On a regular basis, this page will be updated with a "two week outlook of construction activities" of the CTSB. If you have any concerns or questions about this project, you may contact Gregory Meyer, Project Manager, UR Department of Planning and Project Management, at 313-3992.

Additional information about this building can be found on the U of R's web site:

- Please click here to be directed to the CTSB site
- Please click here to see site plan and pictures

Below is the current (Wednesday, June 9, 2010) TWO WEEK OUTLOOK:


To: Upper Mt. Hope Neighborhood Association
From: Gregory Meyer, CTSB Project Manager,
UR Department of Planning and Project Management
Date: Monday, August 2, 2010

Subject:

Outlook of CTSB Construction Activities

___________________________________________________________
For the period: August 2 through August 16, 2010.

Update on last week’s work:
Spray-on fire proofing continued on level 2; exterior air-vapor assemby continued on south elevation; as well as interior mechanical, electrical, plumbing fit-out on 3rd floor. Exterior masonry continued on the north elevation and the east elevation was washed down. Roofing continued on PH and main roofs

Two week outlook:
Masonry operations will continue on north elevation. Envelope, vapor barrier and insulation will continue along north and south elevations. Penthouse mechanical work will continue; roofing operations will continue. Site district chilled water and district hot water installation will continue.

Long term outlook:
The project commenced May 26, 2009. The completion date is anticipated to be March/April, 2011.

As always, please feel free to reach me at 313-3992 (cell) or 276-5256 (field office) with any questions or concerns.

cc: Tom Sullivan-LeChase/Project Manager
Bob DiPaola-URMC/Director/Planning and Project Management
Richard Pifer-URF&S/Associate Vice President/University Facilities and Services
Mary Ockenden-URMC/Associate Vice President and Director/Medical Center Space Planning Office of Government and Community Relations

u m h n @ 2 0 0 9